Flow metrics reference

get_flow_metrics computes these from indexed transition timestamps for one project. Pass since/until (epoch seconds) to window it, and granularity: "day" for daily buckets (default is weekly: the current ISO week plus the preceding five).

The collaboration-shape metrics below measure human attention, not an agent-vs-human split — the question they answer is “where does a human’s time go,” not “who did the work.”

Metric Definition
leadTime ready → done
cycleTime claimed → done
timeInProgress claimed → next stage
reviewLatency in_review → done — the primary human choke point, with a reviewLatencyOverTime trend
agingWip every currently open (in_progress/in_review) issue with its age since claim — a present-state snapshot, not scoped to since/until. Read it against cycleTime’s p50/p90 as reference lines: it surfaces stuck items before they finish and skew the percentiles.

When is an issue “ready”? When it leaves backlog for an open status (todo, or straight into in_progress), or is created in one. An issue that goes from backlog straight to done or cancelled in one update was never ready: it has no lead time, and leadTimeExcluded counts how many such issues finished in the window (leadTime.count is the sample the lead-time percentiles are computed from).

What counts as review? A status is a review step only when it is flagged isReviewStep (create_task_status / update_task_status); the built-in in_review is flagged by default. Entering one requires a completion report when an agent holds the lease, stamps in_review_at, and leaving it for in_progress counts toward reviewLatency, humanInterventions and gateRejections. A status merely named like a review (e.g. “Contract Review”) is not one unless flagged.

Metric Definition
humanInterventions human-authored comments plus status bounces out of review, per completed issue
autonomyRatio lease-held time ÷ cycle time (claimed → done), per completed issue
flowEfficiency lease-held time ÷ lead time (ready → done), for issues completed in the window

autonomyRatio and flowEfficiency look similar but divide by different spans: autonomyRatio excludes queueing time before an issue was claimed; flowEfficiency includes it. A project with a long ready→claimed queue will show a lower flowEfficiency than autonomyRatio even with identical execution.

Metric Definition
wipOverTime work-in-progress (claimed but not done) count per bucket
throughputOverTime issues completed per bucket
cfdOverTime cumulative flow diagram: per-bucket counts of issues in each stage (backlogTodo, inProgress, inReview, done). done is cumulative and never decreases; a widening band between two stages is a choke point.
arrivalVsCompletionOverTime issues created vs. completed per bucket, plus net (created − completed) — answers whether the backlog is growing or burning
bugShareOverTime bug share of completed throughput per bucket (total, bugCount, bugSharePercent). Untyped issues count toward total but never bugCount. A rising trend signals more defects shipping, not just more work.
bugTypeTracked whether a task type keyed bug exists in the workspace at all. false means bug share can’t be computed (no matching type) — distinct from a genuine 0%.

Fault signals for the coordination layer itself, not the work, windowed by since/until:

Metric Definition
leaseExpiries issue leases reclaimed because the holder stopped heartbeating
abandonedClaims file claims released because the agent’s session ended rather than being released deliberately
gateRejections in_review → in_progress bounces specifically — narrower than humanInterventions’ bounce count, which also counts review → cancelled
wipCapPressure claims denied for hitting the project’s per-agent WIP cap

There’s no universally correct WIP limit — the research says so too. Measure your own flow with the metrics above before changing the default cap (see Workflow spec).